5400 SOUTH WIDENING
The Utah Department of Transportation (UDOT) completed a State Environmental Study for 5400 South from Bangerter Highway to 4800 West in the communities of Kearns and Taylorsville. The need to widen 5400 South was identified by local community leaders and formalized in the Wasatch Front Regional Council Long Range Plan. For more information see the Project History.
UDOT will continue to partner with Salt Lake County to communicate with the public during construction. Ongoing public communication will help UDOT improve traffic and safety in the area while minimizing impacts to residents, businesses and the traveling public.
CONSTRUCTION SCHEDULE
PROJECT DETAILS
- Widen 5400 South from five to seven lanes from Bangerter Hwy. to 4800 West
- Reconfigure the 5400 South/4015 West intersection to a ThrU-Turn intersectionto improve traffic flow and safety and to preserve more businesses
- Build a High-T intersection (left-in, left-out), on the south side of 5400 South between Bangerter Hwy. and 4015 West, to improve access to the business park
- Add four new signalized intersections and upgrade four existing signalized intersections
- Add a pedestrian crosswalk with flashing warning lights by the fire station
- Build a six-foot concrete wall along the property lines of homes on the south side of 5400 south from 4270 West to 4580 West
- Widen and add sidewalks along 5400 South and 4015 West to bring them up to UDOT and Americans with Disabilities Act (ADA) standards.
- Add trees on the south side of 5400 South
- Install a drainage system including two fenced detention basins
- Construction contractor: Kilgore
- Funding: $37.6 million
CONSTRUCTION DETAILS
- Work will generally take place from 7 a.m. to 6 p.m. Monday through Friday and most Saturdays
- UDOT will keep two lanes open in the peak direction of traffic during peak-hour traffic
- The schedule is subject to change due to weather conditions and other factors
See Live Traffic in Your Area
Your comments, questions and concerns are important to make this project successful.
Current Activities
5400 SOUTH CONSTRUCTION IS COMPLETE UNTIL NEXT SPRING
Thank you for working with us this year to improve 5400 South for pedestrians, drivers and surrounding communities.
Here is what we were able to bring to your community with your help:
- Two added lanes from 4015 West to Northwest Avenue
- A ThrU-Turn Intersection (TTI) at 5400 South and 4015 West
- New, wider sidewalks, curb and gutter
- An improved drainage system that includes two new detention basins
- Upgraded and coordinated signal timing for new and existing intersections
- A new crosswalk by the fire station to improve pedestrian safety
- Decorative concrete walls and new light posts along 5400 South (provided by Salt Lake County)
Next spring UDOT plans to:
- Complete minor road widening and add sidewalk and a High-T intersection (left-in, left-out access to the old Kmart business park) from Bangerter Highway to 4015 West
- Complete minor road widening, add sidewalk and relocate utilities from Northwest Avenue to 4800 West
- Stripe three-foot shoulders along 5400 South to provide a “Share the Road” area for bicyclists and to improve pedestrian safety
- Plant trees along 5400 South (provided by Salt Lake County)
- Place a surface seal on the entire project roadway