Schedule
This study began in September 2011. UDOT plans to complete the study in the winter of 2012. During the study, the following actions will be accomplished:
- Data Collection Complete: Fall 2011
- Selection of Design Options and Corridor Alternatives: Fall 2011 - Spring 2012
- Concept Level Plans Completed: Summer 2012
- Concept Report Finalized: Summer 2012
- Public Hearings: Late Fall 2012
- Final Environmental Document Approved: Early Spring 2012