Panoramic view of Bluff Street Corridor
85% completion
Map of project
Videos of project
UDOT Traffic
Road Conditions

 

 
BLUFF STREET UPDATE
September 19-26

Work Schedule

Crews are expanding their work day to ensure the project stays on schedule. There will be some night and weekend work throughout the duration of the project. 
  • Night and weekend paving is scheduled September 22 - September 30 (9 p.m. - 6 a.m.), and may include Sunday. There will be nightly street closures during paving operations. Please allow a little extra time if traveling through the project in the evening/nighttime hours. During paving and other operations, the signals may not be perfectly aligned with the travel lanes. Please stay aware and be alert as you enter any controlled intersections within the project.
     
  • Installation of curb, gutter, and sidewalks, etc. will continue this week and next.
     
  • The St. George Marathon takes place on October 6th, and the project has closely coordinated their work to ensure runners will have an acceptable surface to run on.
     
  • Beginning as early as October 7th, expect traffic shifts as crews begin placing the final driving surface throughout the project. Pavement marking will also be taking place beginning soon after the final surface is complete.
     
  • Water connections to properties on the east side of Bluff Street are continuing from 500 North to 900 North. The trenching requires a short closure of accesses while the work is being performed. All stakeholders will be notified as to when they could be impacted.
     
  • Crews have removed asphalt and old base materials at Bluff Street and Sunset Boulevard and are constructing the grade that will complete the northwest portion of the intersection.

TRAVEL ADVISORY  

The speed limit has been reduced to 30 MPH through the construction zone. Thank you for slowing down and keeping workers safe.
 
There are several traffic cameras along the corridor the public can access at any time. Click here for an up-to-the-minute look at project progress and traffic conditions.

ALL BUSINESSES OPEN DURING CONSTRUCTION
To access businesses on the east side of Bluff Street, choosing a side street access is recommended, as most businesses on the east side have rear or side entrances as well as access from Bluff Street. The intersection of 500 North and Bluff street is closed as crews tie in to the new storm drain system. Please access businesses from 500 North or Bluff Street.


PROJECT OVERVIEW
This project is a four-fold undertaking and includes:

  • Upgrading and improving all utilities including storm drain, culinary water, sewer, fiber optics, gas, electrical and an upgraded Advanced Traffic Management System.
  • Increasing capacity by adding an additional northbound and southbound lane from 100 South to 1250 North.
  • Re-configuring the intersection at Sunset Boulevard and Bluff Street to improve traffic flow and increase safety.
  • Adding a dedicated right turn lane from westbound St. George Boulevard to northbound Bluff Street which will improve safety and mobility.
Project completion anticipated for late Fall 2018.
Below: Typical cross-section of Bluff Street upon completion.


Bluff Street is an integrated improvement to enhance the way citizens connect, whether by auto, public transit, cycling, or walking..