PROJECT SCHEDULE

 

Winter 2016
Engineering and Design
 
Right of Way Acquisition
Spring 2016
Right of Way Acquisition continues
Fall 2016
Right of Way Acquisition continues
Winter 2017
Preparatory Utility and Trail Work Begins
Spring 2017
Finish Right of Way and preparatory utility and trail work
Summer 2017
Increase Public Involvement Outreach in preparation for construction
Fall 2017
Project Bids
 
Project is Awarded
 
Preparation for Construction
Winter 2018
Major Construction Begins
Fall 2018
Major Construction is completed