Study Schedule
The following basic timeline provides an overview of the study steps and public process milestones over the life of the study. The study was initiated in September 2007 and was completed in August 2008. UDOT reported the study findings to the Legislature in September 2008.

Study Steps
- Data Collection/Analysis: September 2007 – December 2007
- Alternatives Development: December 2007 – February 2008
- Alternative Refinement/Action Plan Development: February 2008 – August 2008
Public Process Milestones
- Agency Kickoff Meeting – 10/24/07
- Steering Committee Meeting #1 – 12/5/07
- Working Group Meetings, First Set – West, 1/16/08; East, 1/22/08
- Public Open Houses, First Set – Davis, 2/20/08; Weber, 2/21/08
- Working Group Meetings, Second Set – West, 3/19/08; East, 3/20/08
- Steering Committee Meeting #2 – 4/23/08
- Working Group Meetings, Third Set – West, 5/14/08; East, 5/15/08
- Public Open Houses, Second Set – Davis, 6/11/08; Weber, 6/12/08
- Steering Committee Meeting #3 – 7/17/08
|
|