Ramps – Closed nightly
The nights of May 11-17, the northbound on-ramp and southbound off-ramp are scheduled to close from approximately 9 p.m. to 5:30 a.m. for paving and striping. Drivers can use the American Fork Main Street interchange or Lehi 2100 North as an alternate to and from I-15.
NB off-ramp - Closed overnight
The night of May 17, the northbound off-ramp at American Fork Main Street is scheduled to close from 9 p.m. to 5:30 a.m. for sign installation. Lehi Main Street and American Fork 500 East can be used as alternate routes.
NB off-ramp – Closed overnight
As early as the night of May 15, the northbound off-ramp at American Fork 500 East is scheduled to close from 9 p.m. to 5:30 a.m. for sign work. Drivers can use American Fork Main Street as an alternate route.
NB Off-Ramp – Closed overnight
The night of May 22, the northbound off-ramp at Pleasant Grove Boulevard is planned to close from 9 p.m. to 5:30 a.m. for sign work. Drivers can use American Fork 500 East as an alternate route.

SB off-ramp - Closed 30 days
NB on-ramp - Closed 30 days
Continuing through approximately May 23, the southbound off-ramp and the northbound on-ramp at Orem 1600 North will remain closed. During the closure, construction crews will build the new southbound off-ramp and the new northbound on-ramp, as well as the Lindon Park drive connection at 1600 North. Traffic on 1600 North will be restricted to one lane in each direction throughout the closure. Orem Closures Map and Information
University Pkwy – Closed nightly
Through May 18, University Parkway, from 400 West to the I-15 ramps, is scheduled to close nightly from approximately 9 p.m. to 5:30 a.m. for pavement removal and replacement. During these closures, drivers should use 400 West or Geneva Road to access east-west routes, UVU and the business areas. I-15 will remain open. Drivers can also use Orem Center Street, 800 North or Provo Center Street for I-15 access. We recognize these closures will be inconvenient, but they will allow crews to complete the CFI and provide a good alternate route before the 800 North interchange closes. Closures Map
Left turns - Closed
Through May 18, left turns from eastbound and westbound University Parkway to Sandhill Road will not be allowed and traffic lanes will be shifted as work progresses. These restrictions will remain in effect 24 hours a day. Drivers should use 400 West as an alternate route to access area businesses and UVU's campus. During the weekday, westbound drivers on University Parkway may also access the business area on the south side of University Parkway by turning right at Sandhill Road, proceeding through the roundabout at UVU and traveling south through the University Parkway/Sandhill Road intersection.
University Pkwy – Closed 3 days
As early as May 18 at 10 p.m. until May 22 at 5:30 a.m., University Parkway is scheduled to close from 400 West to the I-15 interchange to complete paving, lane marking and signal work and open the University Parkway/Sandhill Road intersection as a CFI. More Information

NB on-ramp - Closed 40 days
The Provo Center Street northbound on-ramp is scheduled to reopen by 5:30 a.m. Friday, May 18.
NB off-ramp – Closed nightly
The nights of May 14-16, the northbound off-ramp to westbound Center Street is scheduled to close from approximately 10 p.m. to 7:30 a.m. for bridge painting. Drivers can use the off-ramp to eastbound Center Street to 900 West to 600 South as an alternate route.
NB off-ramp - Closed overnight
The night of May 16, construction crews are scheduled to close the northbound off-ramp to S.R. 77 from 9 p.m. to 5:30 a.m. to install overhead lighting on the sign structure. Drivers can use the S.R. 75 interchange as an alternate route.
NB on-ramp – Closed overnight
The night of May 15, from 9 p.m. to 5:30 a.m., crews are scheduled to close the northbound on-ramp from Main Street to Northbound I-15 and to eastbound U.S. 6 to install overhead lighting on the sign structure.
Alerts show road or lane closures that may affect travel on I-15, or impact how you get on or off the freeway. For a complete list of all current construction activities, visit the Getting Around page of the project website.
| Stay Informed |
|---|
|
Your comments, questions or concerns are important. To make this project successful we want to hear from you. |