What's Happening Now?
 


The Utah Department of Transportation (UDOT) completed construction of the median barrier and new inside lanes on I-15 from I-84 to 2700 North in Weber County. Travelers are now driving on new pavement. Drivers can expect two lanes in each direction during the day and one lane in each direction at night.

 
Construction Activities 2008
 
    Construction Completed
  • I-15 all lanes in both directions from I-84 to 24th Street
  • 26 bridges in place, decks poured
  • Noise wall installed from I-84 to 31st Street
  • Weber River Bridge
  • 31st Street Interchange
    Items Nearing Completion
  • 24th Street lane additions
  • 21st Street ramps
  • 450 North Interchange
  • 1800 North Overpass
  • 2700 North Interchange
    Upcoming Milestones and Projected Completion Dates
  • Noise walls installed at 21st Street southbound on-ramp - Spring 2008
  • Noise walls installed between 1800 North and 2700 North - Spring 2008
  • 450 North (Pioneer Road) overpass (outside portion) - Spring 2008
  • 12th Street and 12th Street Interchange - Spring/Summer 2008
  • 21st Street Interchange - Summer 2008
  • 2700 North Interchange - Late Summer 2008
    Upcoming Impacts to Motorists
  • Expect traffic impacts as crews work on new lanes and freeway ramps
  • Construction of new lanes and freeway ramps will require motorists to use alternate ramps at various times (Notice will be given ahead of closures.)
  • Paving operations will continue as weather permits
  • Extra caution is advised as traffic can come to an abrupt stop without warning
  • New lanes will be opened and traffic shifted on a regular basis
 
Scheduled Completion - Fall 2008

The project is over 75% complete. For information on project history, click here.