Logan Tenth West
Project Web site: www.udot.utah.gov/tenthwest
Phase One: Work on Phase One of this project, from US-89/91 to 200 North (SR-30) is substantially complete. Some work will be completed this spring, including the bridge deck at the Logan River, some curb and sidewalk, and landscaping.
Phase Two: Phase Two of this project, from 200 North (SR-30) to 2500 North on 1000 West; and from 1000 West to Main Street (US-91) on 2500 North, will begin with utility work in mid-October. Roadway construction will begin as soon as weather permits in the spring of 2013. This phase of the project will include major roadway reconstruction, as well as utility replacements by Logan City. Watch for announcements in the future about the onset of this work.
Project Overview: The Utah Department of Transportation (UDOT) is constructing needed improvements along the state Road 252 corridor, also known as 10th West in Logan. The project limits include 1000 West, from its intersection with S.R. 30 (200 North) on the south, to 2500 North, and from 1000 West to 600 West on 2500 North. The new roadway will be a long-life, 40-year concrete surface.
Project Schedule: Construction activities include utility installations and relocation work and paving between 200 North (SR-30) and 2500 North, and from 1000 West to 600 West on 2500 North. Utility work will get underway in mid-October. Construction work is currently on hold for the winter and will resume in the spring of 2013. Major reconstruction of the corridor is being accomplished in phases. Phase one (from US-89/91 to SR-30/200 North) has been substantially completed.
Project Scope: The roadway design developed for this project will add capacity to meet future roadway use, while responding to corridor and user needs. The general elements of the design are:
Public Involvement: Key involvement activities include site visits and update meetings with property owners, public open houses, local government workshops and formation of a community-based review committee to provide ongoing citizen input and ensure local issues are addressed during construction. See the complete project Web site at www.udot.utah.gov/tenthwest for more details on the public involvement program.
Contact Information: If you have general questions about the Logan 1000 West project or are being impacted by a construction activity as work moves forward, contact the project hotline.Project Hotline: Answers to immediate construction questions and concerns can be obtained by calling toll-free at 888-427-8585, or emailing the Tenth West Project Team.E-mail updates: Join the growing number of your friends, neighbors and businesses who will be getting regular updates on this project via a weekly email alert. For more information, or to get your name on the email list, contact us at tenthwest@utah.gov or call 888-427-8585.