PLANNED CONSTRUCTION SCHEDULE/ACTIVITIES |
 |
2006
-
New signal at 10610 South (in front of the South
Jordan City offices)
-
Utility relocation (power, phone, gas, and cable)
-
Storm drain improvements
-
Water line improvements (South Jordan and Riverton
are upgrading their pipe sizes)
-
Clear/grub (removal of trees and landscaping to
prepare for road widening)
-
Irrigation relocation (after
October 15th when the irrigation lines are dry)
-
Midas Creek box culvert
2007
-
Continue utility relocations
-
New signal at 12300 South
-
Roadway widening and concrete paving
-
Curb and gutter placement
-
Begin driveways and sidewalks
-
Open traffic to 2 lanes each direction
(intermittent restrictions as needed)
2008
|
|
REDWOOD ROAD CONSTRUCTION COMMITTEE (R2C2)
|
 |
The Redwood Road Construction Committee (R2C2) includes representatives from South Jordan and Riverton City, Rosamond Elementary School, Emergency Response, residents, and businesses. The Committee was organized to identify and prioritize construction concerns and to administer the Contractor’s monetary performance incentive based on criteria set by the Committee. The R2C2
is working with UDOT and the contractor during construction to ensure that the needs of the people they represent are being met.
|
|
SCHOOL SAFETY PRESENTATIONS
|
 |
On
7/28/06 and 8/18/06 Safety Presentations were conducted at Rosamond Elementary. Geneva Rock supplied a backhoe, traffic signs, and several safety cones for this presentation.
The school kids were brought out two classes at a time. They were walked through
a maze of several safety cones as we talked to them about what the signs, the
cones, and the caution tape meant. They were shown how the backhoe worked and
what it sounded like. They were instructed to stay away from the construction
and if they needed help crossing the street to ask an adult for help.
Coordination with Rosamond Elementary has been on-going throughout the
construction and hazardous busing is in place.
Click HERE to see pictures of the presentation.
|
|
HAVE YOU SEEN THE LATEST NEWSLETTER?
|
(511 KB)
|
Concrete paving heads north mid-September (11400 South to
10600 South) This newsletter outlines important information you need
to understand about the sequencing steps of this pavement
operation.
(Read More)
|
|
|
| OTHER NEWSLETTERS |
(369 KB)
|
Concrete paving between 12600 South and 11400 South
begins the week of July 9th
This newsletter outlines important information you need
to understand about the sequencing steps of this pavement
operation.
(Read More)
|
|

(137 KB)
|
Design Activities are on Schedule
The Redwood Road Project Team has been working on
finalizing design details and acquiring right-of-way for the
section of Redwood Road between 10400 South in South Jordan
to 12600 South in Riverton for roadway widening and
reconstruction.
(Read More) |
|

(222 KB)
|
Redwood Road (10400 South to Bangerter Hwy)
Last fall, the Draft Environmental Study for Redwood Road
project was completed and circulated for review.
(Read More) |
|
|
|