SR-68 Schedule and Impacts


Project Update: 11/5/09

Segment 2 - Beginning south of Camp Williams and ending just south of the intersection at SR-73 in Saratoga Springs.

  • Crews will begin storm drain work on the southeast corner of the Crossroads. This work will take place in the shoulder with some intermittent traffic shifts.

Segment 1 - Beginning south of the intersection at SR-73 and ending at 400 S. in Saratoga Springs.

  • Crews will continue working on the storm drain on the southeast corner of the Crossroads. This work will take place in the shoulder with some intermittent traffic shifts.
  • Activities in Segment 1 this week include storm drain tie-ins, median work, and paving and will be ongoing for several more weeks. Paving activities are weather dependent and final paving is dependent on utility relocation progress.
  • Rocky Mountain Power continues to be at work in this area removing poles and placing new ones for several more weeks. Once the poles are moved, crews plan to fill the holes and make preparations for the removal of barrels and for traffic to flow normally over the winter.
  • Approved roadside mailboxes continue to be placed along the project. For safety reasons, federal regulations dictate that these new boxes be placed on breakaway posts. Please note, residents should not alter these boxes after they are installed. Any alterations are at risk of removal and replacement at the property owners’ expense.
  • Work on the Pioneer Crossing project continues in the vicinity of 400 N. in Saratoga Springs.

  • If you have questions about the Pioneer Crossing project, please contact their Public Information Team directly:
    Hotline:
    877-222-3757
    Email: access@utah.gov

General Impacts north of SR-73

  • Approved roadside mailboxes continue to be placed along the project. For safety reasons, federal regulations dictate that these new boxes be placed on breakaway posts. Please note, residents should not alter these boxes after they are installed. Any alterations are at risk of removal and replacement at the property owners’ expense.
  • Crews continue on several clean up items and final adjustments throughout the project, including driveways, landscaping, fence, placing road signs and reflectors, and raising manholes to the level of the road. In order for crews to safely work on these items, some brief access interruptions and lane shifts may occur.

Please note that due to weather, project conflicts, or equipment/supply issues, schedules are subject to change.

    More Information
    For additional project information, visit www.udot.utah.gov/sr-68south. For specific questions or concerns, contact the Public Information Team at sr68info@langdongroupinc.com or 801-455-3116.



    Schedule

    The project team began construction operations in April in areas where design and any necessary property acquisitions were complete. A primary priority has been acquiring any necessary right-of-way to construct the project. The design/build team has a project-dedicated right-of-way team for the project. As design is finalized and property impacts are known, this team has been working on a parcel-by-parcel basis with any affected property owners. 

    Work continues on track for completion in summer 2009.