 |
|
Provide Input
Comments on the S.R. 108 project can be submitted at any
time, but comments specifically on the Draft EIS must be
received by January 7, 2008 in order to be
included in the Final EIS. |
|
|
 |
|
| |
| FREQUENTLY ASKED QUESTIONS |
If you have more questions that you would like
answered or listed below, please contact Darla Christiansen at
(800) 252-8929 or
dchristiansen@langdongroupinc.com.
|
|
Q:
|
How many lanes is
UDOT planning to add to this corridor? |
|
A:
|
At the beginning of this study, the S.R. 108
project team conducted a thorough traffic
analysis using both UDOT traffic data and
conducting actual traffic counts throughout the
corridor. Those results were modeled
to determine how many lanes were needed now
through the year 2035. The team found that
5 to 7 lanes would be needed to meet the
projected traffic demand. Because this
road runs through many local communities, the
team decided to pursue the 5-lane alternative,
to minimize impacts to local residents. This
alternative includes two travel lanes in each
direction, shoulders, sidewalks, bike lanes, and
a center median. The drawings below
illustrate the two options being considered for
S.R. 108.
 |
|
Q:
|
Did the traffic study take other projects in
the area into consideration? |
|
A:
|
The project team took several factors into
consideration when conducting the traffic study.
They considered each
city's long range plans as well as
population trends. They also assumed all
projects currently identified on the
Wasatch Front Region Council
(WFRC) Long Range Transportation Plan would
be implemented, including North Legacy Parkway
and improvements to several east-to-west
corridors.
|
|
Q:
|
How will I know
exactly how my property is impacted? |
|
A:
|
Until the EIS is approved and
the design completed, we will not know the exact
impacts of the project. The purpose of an
EIS is to determine possible impacts of a
proposed action. To determine the impacted area,
project engineers developed about 30% of the
design for each of the alternatives. However,
because the design is not complete, the impacts
could change as more details are added in the
final design, which occurs after the EIS is
approved. In the case of relocations, the
project engineers make an assumption for the
study that if the right of-way goes through a
structure, the structure will likely be
relocated. If the right-of-way impacts the
property and comes within 15 feet of a
structure, the structure will be classified as a
potential relocation and if the right-of-way is
more than 15 feet away, only the amount of
property needed for construction will be
acquired. Although the UDOT Right-of-Way
Division uses the EIS as a guidance document,
they look at several factors besides how close
the right-of-way is to a structure when making a
determination about relocation. Each property is
considered independently. The EIS can help
property owners prepare for the possible impact
of the project and once the EIS is approved and
the final design is complete, UDOT right-of-way
agents will work one-on-one with each property
owner to determine if relocation is necessary
and determine fair compensation for private
property impacts.
|
|
Q:
|
If UDOT widens the
road, will they widen from the existing center
line? Or will they widen to one side of
the street? |
|
A:
|
Several
factors are being considered to determine
what alignment the proposed improvements would
follow. In some cases, state and federal
requirements will direct the choice of
alignments. For instance, state or federal
agencies may require that qualifying properties
under section 4(f) of the Department of
Transportation Act of 1966 be avoided. In
other cases, safety and consistency of lanes may
direct the alignment.
|
|
Q:
|
How long is the
EIS Process going to take? When would
construction occur? |
|
A:
|
Environmental Review Process -
The EIS
is projected to take two years (from Summer
2006). A draft of the EIS is scheduled to
be released to the public next summer.
Comments on the draft will then be incorporated
and a final released for public comments in the
winter of 2007. A final decision on the
document is anticipated for summer 2008.
Construction
- There is currently no funding identified
for this project. If the EIS is approved,
funding will need to be identified. The
project will then go into a final design
process. Once the design is complete, UDOT
will begin trying to acquire funds for
construction. We do not yet know how this
project would be segmented or phased for
construction or when construction would occur.
|
|
Q:
|
If we know the
road needs to be widened, why is this study
required? |
|
A:
|
An environmental
review is required for all projects that use
federal funds. By developing this project
in accordance with the National Environmental
Policy Act (NEPA), this project will be eligible for
federal funding, which could improve the
likelihood of finding funding in a more timely
manner.
|
|
| Do you have
questions you would like posted on this site? Comments
and questions regarding the S.R. 108 Environmental Impact
Statement can be directed to Darla Christiansen at (800)
252-8929 or at
dchristiansen@langdongroupinc.com. |
| |
| |
|