Construction Update

SR-193, between State Street and 2000 West, is nearing completion. Crews are preparing
to apply a sealcoat to Center Street in the coming days. During the work, Center Street will be reduced to one lane with flaggers directing traffic from State Street to SR-193. Please choose an alternate route to avoid delays. Other portions of SR-193 will have lane closures during off-peak hours for striping, shoulder work and clean-up efforts.

Crews continue to work on sidewalks, shoulders and landscaping on 700 South west of Main Street. Be aware of construction vehicles occasionally entering or leaving traffic abruptly. Drive the posted speed limit in this corridor and be prepared to stop at any time.

For questions call 800-948-4002 or e-mail SR193@utah.gov.

Lane Closures

• In the coming days, Center Street will be reduced to one lane with flaggers directing traffic from State Street to SR-193. Please choose an alternate route to avoid delays. Other portions of SR-193 will have lane closures during off peak hours for striping, shoulder work and clean-up efforts.

*The schedule is subject to change and is weather dependent.

Please take a look at our project website, if you haven’t yet.
It has additional information you may find helpful. www.udot.utah.gov/sr193

sr193PavementSection(1)

Additional Project Information

▪ Work hours will generally be from 7 am to 5 pm Monday thru Friday, with occasional weekend work when needed

▪ Project completion is scheduled for Summer 2014

Please let us know if you have any questions or comments.
Thanks!

SR-193 Extension Team
800-948-4002