Project Location:
West Bountiful and Woods Cross in Davis County
Project Area Limits:
500 South; Redwood Road to I-15
Project Schedule:
Project Kick-off: Mid-March 2008
Public Involvement: April - December 2008
Acquire Right of Way: May - December 2008
30% Design Completion: May 15, 2008
Public Open House #1: Late May 2008
Early Construction Items: October 2008 - January 2009
60% Design Completion: August 15, 2008
Public Open House #2: Mid September 2008
90% Design Completion: November 17, 2008
Advertise to Contractors for Construction: January 2009
Overview:
This project will reconstruct 500 South into a 5-lane roadway with two lanes in each direction. Additional improvements include 12-foot shoulders to accommodate on street parking, bike lanes, a raised median with intermittent openings in select locations along 500 South, sidewalk, parkstrip, and landscaping.
The purpose of this project is to improve the following:
- Improve future mobility
- Alleviate congestion and improve operating conditions
- Provide safe access to and from properties along the corrideor
- Facilitate safe turning movements
- Accommodate multi-modal uses (pedestrians, cyclists, transit, etc.)
- Correct drainage problems
If you have
any questions regarding this project, please contact the project hotline at 801-904-4112, or email the project team at davis500south@utah.gov |