TIMPANOGOS HIGHWAY (S.R. 92)
PROGRESS UPDATE
Traffic is flowing well on the new Timpanogos Highway (S.R. 92) mainline and drivers are already experiencing the benefits of a safer, improved roadway and interchange. UDOT continues to diligently work with the contractor to address all remaining known quality issues before accepting project completion. UDOT has a responsibility to taxpayers to not accept this project as complete until the contractor corrects any identified quality issues. By insisting that quality standards are met, UDOT is ensuring that the public gets what they paid for and that the road will last for decades to come.
Rest assured, UDOT continues to protect the taxpayer investment from additional costs by charging the contractor $15,000 a day in liquidated damages until the project reaches acceptable completion. With the remaining known work, this project could reach completion this summer.
UDOT continues to work with the contractor to limit lane closures that may be necessary to complete the remaining work to off-commute times and to isolate restrictions to areas only where they are performing work or inspections. Check the website often for updates on lane closures and other remaining work items.
The Timpanogos Highway project will bring a much-needed improvement over the previous roadway including more capacity, a smoother ride, better access to surrounding businesses and increased mobility options. With the addition of the DDI, not originally a part of the project, the interchange can now accommodate current and future traffic demands at I-15. Efficiency and commute times will also be improved with the commuter lanes, providing a no-stopping option for those traveling directly to and from I-15 from the eastern communities.
Triumph Blvd. to Center Street
The outside, eastbound lane on Timpanogos Highway between Triumph Blvd and 1200 West is closed for the next two weeks for barrier work on the south side of the road. Motorists should expect some delays during the evening commute.
Highland Blvd.
Friday, May 18, at 9 p.m. through Monday, May 21, at 6 a.m., crews will close the south leg of Highland Blvd. at the intersection with Timpanogos Highway to make repairs to the pavement. During this closure patrons of the shopping area and residents on 3200 North should plan to use 1200 East to access Timpanogos Highway.
6400 West to S.R. 74
Wednesday, May 16, at 9 p.m. through Sunday, May 20, at 6 p.m., traffic will be reduced to one lane in each direction and shifted to either the north or the south between 6400 West and Town Center Blvd. in Highland. This is necessary so that crews can make repairs to the asphalt on both sides of the road. During this work each side street may be closed for up to five minutes as the grinding machine passes. Flaggers will stop traffic just long enough to allow the grinder to pass. Drivers should plan for heavy delays during the morning and evening commute and should plan extra time to reach their destination.
**All dates are subject to change due to weather or equipment-related issues.**
If you have questions regarding this project or would like additional information, feel free to contact us at 1.877.222.3757, via email at access@utah.gov or visit the project Web site at www.udot.utah.gov/sr92.