State
Street, 10600 South to 9000 South
Crews
on State
Street have started Spring construction.
Upcoming and ongoing activities include placing the raised
and landscaped medians on State Street,
signal
and ATMS installation, sidewalk construction at various locations,
and later this spring, the final asphalt seal coat and final
striping will be completed.
9000 South, Monroe Street to
East of State Street
9000 South is also now under construction. Full reconstruct
of the pavement, widening for turn lanes at State
Street, and utility upgrades are underway.
Two lanes in each direction
are open on 9000 South with lane
shifts to the north.
Anticipated completion date for the State Street,
10600 South to 9000 South is mid- to late summer.
On this web site you can find updated
construction activities, alternate route information, project
team contact information, links to other area projects and
more.
The State Street Project Improvements
include:
o Roadway reconstruction and widening
from 9000 South to 10000 South from five lanes to seven lanes
o Pavement rotomill and overlay from 10000 South to 10600 South
o Full reconstruction of the 10600 South intersection - COMPLETE
o Irrigation canal box culvert reconstruction - COMPLETE
o Burying power lines along the corridor -
COMPLETE
o Constructing continuous sidewalks and curb and gutter
o Improved drainage - COMPLETE
Want to stay up-to-date on the latest State Street construction
activities? If so, join our email list. Simply send your
email address to state90-106@hwlochner.com and
you will be added to the list. Email updates will be sent
to you on a regular
basis. Construction activities will also be recorded
on the project hotline. The hotline number
is (888) 569-4586.
If you have any questions or concerns, please contact
the project team: state90-106@hwlochner.com.
Sincerely,
The State Street,
9000 S. to 10600 S. Team
|