Project Overview
Schedule
Construction Impacts
FAQ
Contact
Map of Area




spacer

 Welcome to the Syracuse Road Project Web Site                                                                          

UDOT is widening Syracuse Road (Antelope Drive) from 1000 West to 2000 West to five lanes - two travel lanes in each direction with a center lane and dedicated bike lanes. The widened roadway will improve traffic flow in the area and improve safety for  local, commuter, and tourist traffic.  Construction on the project began in late February 2009 is anticipated to conclude in late spring 2010.

   



Construction on this project has been scheduled in two phases:

 
Phase I Activities
- Construction began end of February and is now complete!  Thank you for your patience during the first phase.

• New Culinary water line
• New Secondary water line
• Irrigation system improvements
• Demolition

 
Phase II Activities
- Construction began on this phase in June 2009 and is scheduled to be complete in spring 2010.

• Road widening
• Paving
• Intersection improvements including decorative crosswalks at 2000 W. and new signals at both 1000 W. and 2000 W.
• Later sewer line upgrades
• Landscaping
• Lighting
• Storm Drain
• Curb, Gutter and Sidewalk
• Signage, striping
• *Questar will also be working in the area to replace two gas lines

The Syracuse Road Design Process is Innovative

In a traditional construction project, UDOT brings a contractor on for the construction phase only.  On the Syracuse Road project a contractor was brought on during the last phase of design.  The contractor provided feedback to the designers to help with the contructability of the design.  This type of feedback served to shorten the schedule and save money on this project. 


 Project Area

  



Seven Shots from Seven Spots

Check out the project as it progresses!  Each week we will post new photos from the same seven spots on the project.  Look back at previous weeks to see how far we have come.


 Nov. 4, 2009 - Look below this week's Seven Shots for some additional photos of the concrete paving operations

1000 W. Intersection - concrete paving was underway this week in the excavated areas of 1000 W

   

2000 W. Intersection
- now that traffic has been moved onto the new pavement, crews are excavating the old roadway

   

Allison Way - work on a detention pond and utilities is taking place at Allison Way

              
     

 


CLICK HERE TO VIEW PHOTOS FROM PAST WEEKS




Concrete Paving


Sept. 22, 2009