|
| |
| 10th West (SR-252) Project Summary |
|
|
|
Logan 10th West / SR 252
Reconstruction
Project Status and Planned Completion Schedule |
|
Project Elements / Work Area |
Planned Completion* |
|
10th West Frontage Road and Sidewalk |
Complete |
|
Utilities relocation and upgrades |
Complete |
|
Excavation and preparation for paving |
Complete |
|
Logan River Bridge expansion |
Complete |
|
Logan River Bridge deck work |
Spring 2012 |
|
Asphalt tie-ins at intersections on 10th West |
Complete |
|
Storm drain on 2500 North
|
Finish Spring 2012 |
|
Concrete paving on 10th West |
Complete |
|
Final curb, gutter and sidewalks on 10th West |
Spring 2012 |
|
Landscaping (substantial completion) |
Finish Spring 2012 |
|
1000 North & 1400 North signal installations |
Complete |
|
1100 West / US 91 intersection closure - South end of 1100 W |
Complete |
|
Guard rails on the Logan River Bridge |
Complete |
|
Activation of automatic detection systems in the new traffic signals |
Soon |
|
Winter shut down - December 2011 to March 2012 |
In progress |
|
Final landscaping, punch list and project clean up |
Spring 2012 |
|
2500 North Roadwork - 600 West to Main St. (US 89/91) |
Pending permit |
|
* This schedule is contingent on work conditions, changes in project needs and weather. |
|
| |
| |
|
Phase I Project Update: JAN 2012
General Status:The majority of work on Phase I of the 10th West project (US 89/91 to 200 North) has been completed as outlined in the Project Status list below.
While some workers will continue to work on completing "punch list" items within the corridor over the next several weeks, all intersection and paving work is complete and all lanes are open to traffic.
Upcoming Work:In the coming weeks workers will, as weather allows, complete the installation of new signs throughout the construction zone.
Crews will also complete remaining roadway striping and other pavement painting, and complete landscaping improvements as weather permits. Motorists are encouraged to be watchful for workers engaged in these activities adjacent to, or within the new lanes of travel and to approach such work with caution.
Speed Limit and Speed Study:During the environmental phase, the project team stated that that they were not proposing a change in the speed limit. However, it was also conveyed during the environmental study and design phase of the project that UDOT had agreed to conduct a traffic speed study after road construction was complete in order to determine an appropriate speed limit for the new roadway configuration. It is understandable how this information could have been interpreted to mean that the speed limit would not change, and the project team apologizes for any confusion. The objective of the speed study is to determine the speed limit that safely meets motorist expectations, while providing safety for pedestrians and adjacent property owners. Until the speed study is completed and new signs are installed to reflect the results of the study, motorists are expected to continue to obey the temporary posted speed limits.
|
| |
| |
|
Phase II Project Status
Phase II is planned to begin in the Spring. For specific information on the Phase II project, please visit the Phase II web site at: www.udot.utah.gov/10thwestphaseII
|
| |
| |
|
Project Status
Update: SEPT 2011
Traffic Control: Traffic movement, including access to businesses and residences is intended to be maintained at all times, with shifts from east to west as needed to accommodate paving. Temporary closures and detours may occur.
Travel During Construction: UDOT encourages continued patronage of local businesses on 10th West and 2500 North during construction. However, if your destination is not on 10th West or 2500 North, please use alternate routes.
Please drive slowly through construction areas.
Project Status
Update: JUNE 2011
Beginning
Sunday, June 19, 2011 and continuing for approximately 60
days, access to and from 10th West/SR 252 between 600 South
and 400 North will be limited to local access only. This
closure to thru-traffic is to allow Logan City to replace a
failing sewer line that was recently discovered and was not
part of the original project. This work will also allow for
accelerated road work in this area.
Please follow this link for more information.
Project Status
Update: MAY 2011
Construction
Begins
Project Description: The project follows the recently completed environmental document to improve
the safety and capacity of 10th West/SR 252 and 2500 North and bring the route up to state standards. On
10th West, work will include widening the roadway to five lanes from US 91 to 300 North (including
the Logan River Bridge) and a new west-side frontage road between 600 South and 200 South.
Traffic signals and turn lanes will also be installed at 10th North and 14th North. On 2500 North
work will include widening to five lanes from 600 West to Main St., plus two left turns onto Main
St. As part of the project, the contractor will also close the north side of the 1100 West/US 91
intersection, as discussed during the environmental process. UDOT has selected Staker Parson
Company as the general contractor. For background on the entire project, see the completed
environmental document at Final Environmental Study.
General Project
Schedule and Approach:
Construction work on the project is planned to begin on
approximately February 28th and conclude with substantial
completion by the end of Winter. The approach to the
project is organized into five general activities; 1)
utilities relocation and upgrades, 2) Logan River Bridge
widening, 3) roadway excavation, 4) paving and 5)
landscaping and cleanup. Many of the activities will occur
simultaneously.
-
Daily Work Schedule: The
contractor plans to work six days per week, (Monday
through Saturday) from approximately 7 a.m. to 7 p.m.
Exceptions may include occasional night work for utility
connections (as allowed by the City of Logan) or if
needed to respond to weather or significant project
conditions.
-
Traffic Control:
Traffic movement,
including access to businesses and residences on 10th
West and 2500 North is intended to be maintained at all
times, with minor exceptions for closures as needed for
utility work and to allow paving to cure. Intermittent
detours may also occur.
-
Use of 10th West
and 2500 North during Construction:
UDOT encourages continued
patronage of local businesses on 10th West and 2500
North during construction. However, if your destination
is not on 10th West or 2500 North, the contractor
encourages travelers to use alternate routes.
Please drive slowly through construction areas.
-
Property / Business Owner Coordination:
The public
involvement team will provide information to affected
property and business owners through several actions.
–
direct mailings
such as invitations to meetings, project updates
and newsletters will be sent to affected
property and business owners as needed during
the project. To be sure you are added to the
mailing list, please send an e mail with your
current postal delivery address to:
tenthwest@utah.gov
“Neighborhood” meetings
–
meetings for
property and business owners in specific areas
affected by the project. Invitation to meetings
will be sent via direct mailings.
Web page – the
project web page will provide overall project
information and will be updated periodically
with significant changes in project activities
or schedule.
Weekly email updates –
brief project
status emails will be sent out each week to
describe current project activities, traffic
control and upcoming actions. To subscribe to
the email distribution list, please send an e
mail to:
tenthwest@utah.gov
Follow
the project on Twitter at:
http://twitter.com/tenthwest and soon to be on
Facebook
Community Review Board:
A
local committee,
consisting of affected and interested residents and
business owners, representatives from Logan City, Cache
County, Logan School District, and other key
stakeholders, will be formed to provide input to the
contractor and UDOT during the project. Members of the
committee will also serve as liaisons to others
regarding the project. The committee will meet with the
project team once per month during construction.
Project Assistance
Hot Line:
For quick response to address
“on-the-ground” issues and concerns, please call
1-888-427-8585.
Project Email:
Questions and concerns
regarding the project can also be addressed via the
project
e-mail at:
tenthwest@utah.gov
Local Media:
Please consult the local
newspaper for periodic project updates and other
significant project activities.
UDOT Media Contact:
UDOT Region 1 Public
Involvement Manager
Vic Saunders
1-801-620-1641
vsaunders@utah.gov
|
|
|
|
|