| Meeting Summary and
Schedule |
 |
Specific times and locations for public open
house meetings will be announced through the
local media. Individual invitations will be sent
for TAC meetings, Property/Business Owners
meetings, and Local Government meetings. |
|
|
Committees:
Public Open Houses = Open to Everyone
TAC = Technical Advisory Council
Property/Business Owner Meeting = Focused on Affected
Owners/Corridor Interests
LG = Local Government Meeting |
|
April 2008:
May 2008:
-
Public Open House -
Introduction (May 1, 2008, 6:00 -
8:00 PM at Woodruff Elementary)
Public Meeting Results
-
Local Government Meeting #1 - Introduction (combined) (May 1, 2008)
-
Scoping Meeting (Thursday, May 29)
Break in Public Involvement Activities:
Public involvement activities were suspended June through
August to allow additional time for data gathering and
technical analysis, and to develop the conceptual design.
September 2008:
-
Local Government Meeting #2
– Tues, September 23, 2008 – Conceptual Design
-
TAC Meeting #2
– Wed, September 24, 2008 – Conceptual Design Workshop
Meeting Results
October 2008:
-
Continue Property Site Visits
-
Neighborhood
Association Meeting #2
– Mon, October 20, 2008 – Conceptual Design
Meeting Results
-
PTA Group Meeting #2
– Tues, October 21, 2008 –
Meeting
Results
-
Public Open House #2
– Tues, October 21, 2008 – 6 to 8 p.m. at Woodruff
Elementary School – Conceptual Design,
Meeting Results
-
Property/Business Owner Meeting #1
– Wed, October 22, 2008 – Conceptual Design / Property
Issues,
Meeting Results
April 2009:
-
TAC Meeting #3
– Draft Design – April 13, 2009,
Meeting Results
-
Local Government Meeting #3
- Final Draft Design / Planned Construction Approach and
Schedule – April 27, 2009,
Meeting Results
-
Continue Property Site Visits as needed April -
Summer 2009
May 2009:
-
Continue Property Site Visits as needed May -
Summer 2009
-
Residential Property Owner Meeting -
Discuss widened design alternatives and possible
alignments as well as variants of previous design
concept -
May
26, 2009,
Meeting
Results
-
Design Group
Work Session
- Develop specific design for buffer area -
May
27, 2009,
Meeting Results
-
UDOT Internal Design Meeting
- May 2009
June / July
2009:
-
Continue Property Site Visits as needed June -
Summer 2009
-
Property / Business Owner Meeting #2
– Final Draft Design / Planned Construction Approach and
Schedule – June 2009,
Meeting Results
-
TAC Meeting #4
– Present preliminary proposed design - June 2009,
Meeting Results
-
Public
Meeting # 3
- Present
proposed design - July 15, 5:30 - 7:30 PM at
Woodruff Elementary School,
Meeting
Results,
Preliminary Design Maps from Meeting
-
Woodruff Elementary PTA Meeting -
Present proposed design -
July 15,
Meeting
Results
August
2009:
- 1100
West Property Owner/Neighborhood Meeting - August 4, 2009, 6-7:00
PM, Cache County Building Room #109 (Invitation),
Meeting Results
-
TAC Meeting #5
–
Confirm proposed design -
August 4, 2009,
Meeting
Results
September
2009:
-
UDOT Preliminary Design Review Meeting
–
Confirm proposed design
- Final
Design
Property Owner Meetings - Access & Driveways
(On-going)
November
2009:
-
Continue Property Site visits as needed
December
2009 /
January 2010:
-
Individual Property Acquisition Meetings to begin
|
|