Logan 10th West / SR 252
Reconstruction
Project Status and Planned Completion Schedule |
|
Project Elements / Work Area |
Planned Completion* |
|
10th West Frontage Road and Sidewalk |
Complete |
|
Utilities relocation and upgrades |
Complete |
|
Excavation and preparation for paving |
Complete |
|
Logan River Bridge expansion |
Complete |
|
Logan River Bridge deck work |
Spring 2012 |
|
Asphalt tie-ins at intersections on 10th West |
Complete |
|
Storm drain on 2500 North
|
Finish Spring 2012 |
|
Concrete paving on 10th West |
Complete |
|
Final curb, gutter and sidewalks on 10th West |
Spring 2012 |
|
Landscaping (substantial completion) |
Finish Spring 2012 |
|
1000 North & 1400 North signal installations |
Complete |
|
1100 West / US 91 intersection closure - South end of 1100 W |
Complete |
|
Guard rails on the Logan River Bridge |
Complete |
|
Activation of automatic detection systems in the new traffic signals |
Soon |
|
Winter shut down - December 2011 to March 2012 |
In progress |
|
Final landscaping, punch list and project clean up |
Spring 2012 |
|
2500 North Roadwork - 600 West to Main St. (US 89/91) |
Pending permit |
|
* This schedule is contingent on work conditions, changes in project needs and weather. |