Logan 10th West / SR 252 Reconstruction

Project Status and Planned Completion Schedule

Project Elements / Work Area

Planned Completion*

10th West Frontage Road and Sidewalk

Complete

Utilities relocation and upgrades

Complete

Excavation and preparation for paving

Complete

Logan River Bridge expansion

Complete

Logan River Bridge deck work

Spring 2012

Asphalt tie-ins at intersections on 10th West

Complete

Storm drain on 2500 North

Finish Spring 2012

Concrete paving on 10th West

Complete

Final curb, gutter and sidewalks on 10th West

Spring 2012

Landscaping (substantial completion)

Finish Spring 2012

1000 North & 1400 North signal installations

Complete

1100 West / US 91 intersection closure - South end of 1100 W

Complete

Guard rails on the Logan River Bridge

Complete

Activation of automatic detection systems in the new traffic signals

Soon

Winter shut down - December 2011 to March 2012

In progress

Final landscaping, punch list and project clean up

Spring 2012

2500 North Roadwork - 600 West to Main St. (US 89/91)

Pending permit

* This schedule is contingent on work conditions, changes in project needs and weather.