 Project Summary
30-JUN-2025
US-89 at Main St/200 E, American Fork
347.49
347.97
13061
Project Completed
$2,450,249
Region 3
UTAH
Roadway
Design, Bid, Build

   

 Contact Information
Eric A Mason
(801) 680-9472
emason@utah.gov

   

 Project Construction Information
HIDDEN PEAK ELECTRIC CO., INC.
$1,558,762
June 2017
100 %

   

 Expenditures by Category   As of 30-JUN-2025
$0
$205,254
$1,670,646
$0
$283,793
$144,141
$61,864
$84,551
$0
$2,450,249

 Total Expenditures by Funding Source   As of  30-JUN-2025

Source Funding Expenditures
Federal $2,078,224 $2,078,224
State $246,955 $246,955
Local $125,070 $125,070
Report Total: $2,450,249 $2,450,249

 Total Project Funding   As of  30-JUN-2025

Fund Funding Expenditures
STP_URB_P/O $233,075 $233,075
STP_FLX_MAG $101,852 $101,852
ST_MATCH $16,925 $16,925
ST_SIGNALS $5,291 $5,291
ST_SPOT_SFTY $150,000 $150,000
ST_CONT_R3 $74,738 $74,738
L_BETTERMENT $125,070 $125,070
CMAQ_MAG $425,000 $425,000
CMAQ_PM2.5 $1,318,297 $1,318,297
Report Total: $2,450,249 $2,450,249

   

US-89 at Main St/200 E, American Fork - Pin: 13061
( UTAH County )
 White Pin- Planned   Light Blue Pin- Awarded   Blue Pin- Close Out 
 Yellow Pin- In Design   Green Pin- Under Construction   Pink Pin- Project Completed 
 Orange Pin- Advertised   Red Pin- Construction Complete   Purple Pin- Hold 
  
  • Utah.gov Home
  • Utah.gov Terms of Use
  • Utah.gov Privacy Policy
  • Translate Utah.gov

Copyright © 2025 State of Utah - All Rights Reserved.