 Project Summary
30-APR-2025
I-15; 1800 North Interchange & Corridor Widening
336.2
338.2
15682
Close Out
$385,304,975
Region 1
Capacity
Design, Bid, Build

   

 Contact Information
Nathan D Hipp
(801) 471-6316
nhipp@utah.gov

   

 Project Construction Information
RLW/WHITAKER, A JOINT VENTURE, L.P.
$196,451,989
March 2025
100 %

   

 Expenditures by Category   As of 30-APR-2025
$0
$372,652
$16,184,579
$0
$20,408,244
$32,074,571
$1,325,248
$795,168
$0
$71,160,462

 Total Expenditures by Funding Source   As of  30-APR-2025

Source Funding Expenditures
State $376,441,841 $68,788,549
Local $8,863,134 $2,371,913
Report Total: $385,304,975 $71,160,462

 Total Project Funding   As of  30-APR-2025

Fund Funding Expenditures
ST_TIF $375,584,000 $67,930,708
ST_APPROP $857,841 $857,841
LOCAL_GOVT $8,863,134 $2,072,686
OTHR   $299,227
Report Total: $385,304,975 $71,160,462

   

I-15; 1800 North Interchange & Corridor Widening - Pin: 15682
( Region 1 )
 White Pin- Planned   Light Blue Pin- Awarded   Blue Pin- Close Out 
 Yellow Pin- In Design   Green Pin- Under Construction   Pink Pin- Project Completed 
 Orange Pin- Advertised   Red Pin- Construction Complete   Purple Pin- Hold 
  
  • Utah.gov Home
  • Utah.gov Terms of Use
  • Utah.gov Privacy Policy
  • Translate Utah.gov

Copyright © 2025 State of Utah - All Rights Reserved.