 Project Summary
31-MAY-2025
600 North to SR-9 in Hurricane
4270
Project Completed
$2,817,146
Region 4
WASHINGTON
Reconstruction
Design, Bid, Build

   

 Contact Information
Kerry W. Savage
(435) 201-2029

   

 Project Construction Information
Old do not use A-T ASPHALT PAVING
$1,830,860
September 2009
100 %

   

 Expenditures by Category   As of 31-MAY-2025
$0
$58,366
$1,831,546
$154,159
$208,051
$565,023
$0
$0
$0
$2,817,146

 Total Expenditures by Funding Source   As of  31-MAY-2025

Source Funding Expenditures
Federal $2,456,616 $2,456,616
Local $360,530 $360,530
Report Total: $2,817,146 $2,817,146

 Total Project Funding   As of  31-MAY-2025

Fund Funding Expenditures
STP_FLX_JHC $1,072,616 $1,072,616
LOCAL_GOVT $360,530 $360,530
FS_STP_JHC $1,384,000 $1,384,000
Report Total: $2,817,146 $2,817,146

   

600 North to SR-9 in Hurricane - Pin: 4270
( WASHINGTON County )
 White Pin- Planned   Light Blue Pin- Awarded   Blue Pin- Close Out 
 Yellow Pin- In Design   Green Pin- Under Construction   Pink Pin- Project Completed 
 Orange Pin- Advertised   Red Pin- Construction Complete   Purple Pin- Hold 
  
  • Utah.gov Home
  • Utah.gov Terms of Use
  • Utah.gov Privacy Policy
  • Translate Utah.gov

Copyright © 2025 State of Utah - All Rights Reserved.