The Utah Department of Transportation (UDOT) advises motorists and recreationalists of a pavement rehabilitation project beginning in Morgan County on SR-65 from the Salt Lake County line (milepost 8) to the Summit County line (milepost 22) and SR-66 from the Porterville area (milepost 9) to East Canyon Reservoir (milepost 0). The project includes the removal of the top layer and placement of a new layer of asphalt paving. New guardrail will be installed in selected areas along the project corridors. Work scheduled during the daytime hours will be Monday through Friday, and weekend work will be scheduled as needed. All work is weather-dependent.
WHAT TO EXPECT:
• During construction, pilot cars will be used to direct one-way traffic through work zones. Motorists should expect delays. • Business and residential accesses will be maintained. Very brief closures are possible when equipment is passing by residential and business driveways. • Noise and lighting impacts are possible during work hours. • Cyclists are advised to avoid the area as much as possible during construction as asphalt removal will result in rougher riding conditions. When this is not possible, cyclists should drive with traffic and not attempt to pass other vehicles. Cyclists are required to stop at the flaggers with other traveling public.
TENTATIVE WORK SCHEDULE FOR SUMMER 2020:
Please note that due to weather conditions, emergency situations or equipment/supply issues, schedules are subject to change.
• July 3rd - July 6th
Work will be suspended for the Independence Day weekend, starting on Friday July 3rd until the morning of Monday July 6th.
• July 6 - July 20
Crews expect to finish up guardrail installations and start chip seal operations on Monday, July 6th. Work will begin on SR-65 near the Salt Lake County line (Big Mountain summit) and progress northbound. Work will move to SR-66 when SR-65 is complete. Chip seal operations are estimated to take approximately two weeks. Flagging operations and pilot cars will help direct drivers and cyclists through work zones.
• July 20 - July 24:
Crews will complete chip seal operations and place permanent pavement markings and messages. Installation of guardrail will be conducted throughout the duration of the project.
• July 20 - July 31:
Final roadway clean-up and project completion.
Project impacts to travel can be found on the UDOT Traffic website, www.udot.utah.gov/traffic. *More info about this project is available by calling the project hotline at 385-515-0441.
More information is available by contacting the project public information team. Please contact the project hotline at 385-515-0441 or send an email to pyocom@langdongroupinc.com if you would like to receive email updates.