 Project Summary
31-OCT-2026
I-15; N. Cedar to Summit & SR-130; N. Cedar Main
61.372
70.25
15333
Project Completed
$13,477,225
Region 4
IRON
Rehabilitation
Design, Bid, Build

   

 Contact Information
Samuel B. Grimshaw
(435) 592-1226

   

 Project Construction Information
SUNROC CORPORATION
$11,221,243
May 2020
100 %

   

 Expenditures by Category   As of 31-OCT-2026
$0
$1,190,102
$12,038,170
$6,381
$235,074
$0
$0
$7,497
$0
$13,477,225

 Total Expenditures by Funding Source   As of  31-OCT-2026

Source Funding Expenditures
Federal $13,477,225 $13,477,225
Report Total: $13,477,225 $13,477,225

 Total Project Funding   As of  31-OCT-2026

Fund Funding Expenditures
STP_FLX_ST $13,477,225 $13,477,225
Report Total: $13,477,225 $13,477,225

   

I-15; N. Cedar to Summit & SR-130; N. Cedar Main - Pin: 15333
( IRON County )
 White Pin- Planned   Light Blue Pin- Awarded   Blue Pin- Close Out 
 Yellow Pin- In Design   Green Pin- Under Construction   Pink Pin- Project Completed 
 Orange Pin- Advertised   Red Pin- Construction Complete   Purple Pin- Hold 
  
  • Utah.gov Home
  • Utah.gov Terms of Use
  • Utah.gov Privacy Policy
  • Translate Utah.gov

Copyright © 2026 State of Utah - All Rights Reserved.