 Project Summary
31-DEC-2022
I-70/I-15 Interchange Deck Replacements
0
1.154
18256
Under Construction
$6,700,000
Region 4
MILLARD
Structures
Design, Bid, Build

   

 Contact Information
Maicah A May Anderson
(435) 287-5319
maanderson@utah.gov

   

 Project Construction Information
W. W. CLYDE & CO
$5,370,202
April 2022
86 %

   

 Expenditures by Category   As of 31-DEC-2022
$0
$357,154
$4,406,600
$0
$556,482
$0
$0
$0
$0
$5,320,235

 Total Expenditures by Funding Source   As of  31-DEC-2022

Source Funding Expenditures
Federal $6,700,000 $5,320,235
Report Total: $6,700,000 $5,320,235

 Total Project Funding   As of  31-DEC-2022

Fund Funding Expenditures
STP_BRIDGE $990,000 $0
NHPP_BR $5,710,000 $5,320,235
Report Total: $6,700,000 $5,320,235

   

I-70/I-15 Interchange Deck Replacements - Pin: 18256
( MILLARD County )
 White Pin- Planned   Light Blue Pin- Awarded   Blue Pin- Close Out 
 Yellow Pin- In Design   Green Pin- Under Construction   Pink Pin- Project Completed 
 Orange Pin- Advertised   Red Pin- Construction Complete   Purple Pin- Hold 
  
  • Utah.gov Home
  • Utah.gov Terms of Use
  • Utah.gov Privacy Policy
  • Translate Utah.gov

Copyright © 2023 State of Utah - All Rights Reserved.