 Project Summary
31-MAY-2025
I-70/I-15 Interchange Deck Replacements
0
1.154
18256
Project Completed
$6,586,913
Region 4
MILLARD
Structures
Design, Bid, Build

   

 Contact Information
Justin Christensen
(435) 406-9129
jchristensen2@utah.gov

   

 Project Construction Information
W. W. CLYDE & CO
$5,397,702
April 2022
100 %

   

 Expenditures by Category   As of 31-MAY-2025
$0
$477,816
$5,547,429
$0
$559,515
$0
$0
$2,153
$0
$6,586,913

 Total Expenditures by Funding Source   As of  31-MAY-2025

Source Funding Expenditures
Federal $6,586,913 $6,586,913
Report Total: $6,586,913 $6,586,913

 Total Project Funding   As of  31-MAY-2025

Fund Funding Expenditures
STP_BRIDGE $898,346 $898,346
NHPP_BR $5,688,567 $5,688,567
Report Total: $6,586,913 $6,586,913

   

I-70/I-15 Interchange Deck Replacements - Pin: 18256
( MILLARD County )
 White Pin- Planned   Light Blue Pin- Awarded   Blue Pin- Close Out 
 Yellow Pin- In Design   Green Pin- Under Construction   Pink Pin- Project Completed 
 Orange Pin- Advertised   Red Pin- Construction Complete   Purple Pin- Hold 
  
  • Utah.gov Home
  • Utah.gov Terms of Use
  • Utah.gov Privacy Policy
  • Translate Utah.gov

Copyright © 2025 State of Utah - All Rights Reserved.