 Project Summary
30-JUN-2025
I-70; Sevier County Line to Belknap
7.37
17.788
18378
Project Completed
$2,141,975
Region 4
SEVIER
Preservation
Design, Bid, Build

   

 Contact Information
Larry Johnson
(801) 870-4298
lrjohnson@utah.gov

   

 Project Construction Information
ADVANCED PAVING AND CONSTRUCTION LLC
$1,890,530
July 2023
100 %

   

 Expenditures by Category   As of 30-JUN-2025
$0
$95,275
$2,020,300
$0
$26,400
$0
$0
$0
$0
$2,141,975

 Total Expenditures by Funding Source   As of  30-JUN-2025

Source Funding Expenditures
Federal $2,141,975 $2,141,975
Report Total: $2,141,975 $2,141,975

 Total Project Funding   As of  30-JUN-2025

Fund Funding Expenditures
STP_SU_JHC $290,000 $290,000
NHPP_IM $1,851,975 $1,851,975
Report Total: $2,141,975 $2,141,975

   

I-70; Sevier County Line to Belknap - Pin: 18378
( SEVIER County )
 White Pin- Planned   Light Blue Pin- Awarded   Blue Pin- Close Out 
 Yellow Pin- In Design   Green Pin- Under Construction   Pink Pin- Project Completed 
 Orange Pin- Advertised   Red Pin- Construction Complete   Purple Pin- Hold 
  
  • Utah.gov Home
  • Utah.gov Terms of Use
  • Utah.gov Privacy Policy
  • Translate Utah.gov

Copyright © 2025 State of Utah - All Rights Reserved.