30-APR-2023
Region 4 Culvert Program, Phase 10
2.95
5
19130
Under Construction
$1,250,000
Region 4
IRON
Transportation Solutions
Design, Bid, Build

   

 Contact Information
Robert Lamoreaux Udot
(435) 817-5371
lamoreauxbob@stanleygroup.com

   

 Project Construction Information
SKYVIEW EXCAVATION AND GRADING, INC.
$845,186
March 2023
54 %

   

 Expenditures by Category   As of 30-APR-2023
$0
$103,796
$393,100
$0
$106,173
$0
$0
$0
$0
$603,069

 Total Expenditures by Funding Source   As of  30-APR-2023

Source Funding Expenditures
State $1,250,000 $603,069
Report Total: $1,250,000 $603,069

 Total Project Funding   As of  30-APR-2023

Fund Funding Expenditures
ST_TRANS_SOL $143,008 $0
ST_PVMT_LV2 $450,000 $16,078
ST_PVMT $586,992 $586,992
ST_BARRIER $70,000 $0
Report Total: $1,250,000 $603,069

   

Region 4 Culvert Program, Phase 10 - Pin: 19130
( IRON County )
 White Pin- Planned   Light Blue Pin- Awarded   Blue Pin- Close Out 
 Yellow Pin- In Design   Green Pin- Under Construction   Pink Pin- Project Completed 
 Orange Pin- Advertised   Red Pin- Construction Complete   Purple Pin- Hold 
  
  • Utah.gov Home
  • Utah.gov Terms of Use
  • Utah.gov Privacy Policy
  • Translate Utah.gov

Copyright © 2023 State of Utah - All Rights Reserved.