The Utah Department of Transportation (UDOT) widened S.R. 198 between Woodland Hills Drive and Arrowhead Trail Road in Spanish Fork and Salem. Construction began in May 2019 and was complete by fall 2020. In addition to the widening, a multi-use trail along the east side of S.R. 198 was constructed for cyclists and pedestrians. These improvements will reduce congestion, address future travel demand and enhance safety and trail connectivity. A list of the improvements is provided below.
Improvements
Additional travel lane in each direction
New multi-use trail
Drainage upgrades
Signal upgrade at Woodland Hills Drive
This project was completed in October 2020.
UDOT Region Three
801-227-8000