Project Construction Information |
Expenditures by Category As of 31-DEC-2022 |
Total Expenditures by Funding Source As of 31-DEC-2022 |
|
Source |
Funding |
Expenditures |
Federal |
$24,175,099 |
$23,192,195 |
Local |
$2,092,997 |
$2,092,997 |
State |
$46,516 |
-$627,793 |
Report Total: |
$26,314,611 |
$24,657,399 |
| |
Total Project Funding As of 31-DEC-2022 |
|
Fund |
Funding |
Expenditures |
STP_UB_P/O_U |
$12,331,409 |
$12,229,706 |
STP_FLX_ST |
$367,881 |
$0 |
ST_PVMT_LV2 |
$40,000 |
$3,378 |
ST_CONCPT_D3 |
$6,516 |
$6,516 |
NHPP_NHS |
$9,175,809 |
$8,662,489 |
L_BETTERMENT |
$2,092,997 |
$2,092,997 |
HSIP |
$2,300,000 |
$2,300,000 |
OTHR |
|
-$637,687 |
Report Total: |
$26,314,611 |
$24,657,399 |
| |
|
- Planned |
- Awarded |
- Close Out |
- In Design |
- Under Construction |
- Project Completed |
- Advertised |
- Construction Complete |
- Hold |
|
|