• Home
  • About This Site
  • UDOT Home
  • Contact Us
  • Login
    UDOT Logo PROJECTS    


  •     HOME   
  •    DETAILS   
  •    PHOTOS   
  •    DOWNLOADS   
  

   

   

 Project Summary
31-MAY-2025
I-15; Lehi Main to SR-92, Technology Corridor
277.78
285.01
12158
Close Out
$406,006,539
Region 3
UTAH
Capacity
Design - Build

   

 Contact Information
Boyd Humpherys
(435) 452-2057
bhumpherys@utah.gov

   

 Project Construction Information
AMES-WADSWORTH JOINT VENTURE
$318,712,593
January 2018
100 %

   

 Expenditures by Category   As of 31-MAY-2025
$1,021
$6,638,850
$319,398,367
$0
$29,395,304
$24,616,331
$7,517,009
$15,035,110
$0
$402,601,993

 Total Expenditures by Funding Source   As of  31-MAY-2025

Source Funding Expenditures
State $405,701,021 $402,296,475
Local $305,518 $305,518
Report Total: $406,006,539 $402,601,993

 Total Project Funding   As of  31-MAY-2025

Fund Funding Expenditures
ST_TIF $404,873,280 $401,468,734
ST_GF_HB173 $10,000 $10,000
ST_APPROP $816,720 $816,720
ST_CONCPT_D3 $1,021 $1,021
OTHER $51,440 $51,440
L_BETTERMENT $254,079 $254,079
Report Total: $406,006,539 $402,601,993

   

I-15; Lehi Main to SR-92, Technology Corridor - Pin: 12158
( UTAH County )
 White Pin- Planned   Light Blue Pin- Awarded   Blue Pin- Close Out 
 Yellow Pin- In Design   Green Pin- Under Construction   Pink Pin- Project Completed 
 Orange Pin- Advertised   Red Pin- Construction Complete   Purple Pin- Hold 
  
  • Utah.gov Home
  • Utah.gov Terms of Use
  • Utah.gov Privacy Policy
  • Translate Utah.gov

Copyright © 2025 State of Utah - All Rights Reserved.