 Project Summary
30-APR-2023
I-15; Lehi Main to SR-92, Technology Corridor
277.78
285.01
12158
Construction Complete
$415,106,539
Region 3
UTAH
Capacity
Design - Build

   

 Contact Information
Boyd Humpherys
(435) 452-2057
bhumpherys@utah.gov

   

 Project Construction Information
AMES-WADSWORTH JOINT VENTURE
$318,275,163
January 2018
100 %

   

 Expenditures by Category   As of 30-APR-2023
$1,021
$6,362,606
$318,979,731
$0
$29,311,658
$24,536,729
$7,517,009
$15,025,560
$0
$401,734,314

 Total Expenditures by Funding Source   As of  30-APR-2023

Source Funding Expenditures
State $414,801,021 $401,428,796
Local $305,518 $305,518
Report Total: $415,106,539 $401,734,314

 Total Project Funding   As of  30-APR-2023

Fund Funding Expenditures
ST_TIF $413,973,280 $400,601,055
ST_GF_HB173 $10,000 $10,000
ST_APPROP $816,720 $816,720
ST_CONCPT_D3 $1,021 $1,021
OTHER $51,440 $51,440
L_BETTERMENT $254,079 $254,079
Report Total: $415,106,539 $401,734,314

   

I-15; Lehi Main to SR-92, Technology Corridor - Pin: 12158
( UTAH County )
 White Pin- Planned   Light Blue Pin- Awarded   Blue Pin- Close Out 
 Yellow Pin- In Design   Green Pin- Under Construction   Pink Pin- Project Completed 
 Orange Pin- Advertised   Red Pin- Construction Complete   Purple Pin- Hold 
  